Management of change (MOC) and pre-startup safety review, explained
Why changes to machines, materials and ways of working lead to so many serious incidents, what OSHA's process safety rule requires for MOC and pre-startup safety review (PSSR), and how any site can review a change before it starts.
Checked against its sources on November 25, 2026 · By PraxysEHS
The short version
- Change brings hazardsWhy MOC existsA new machine, chemical, layout or procedure can bring hazards nobody has looked at yet.
- Review it firstManagement of changeLook at a change's hazards and decide what it needs before it's bought, built or started.
- Check before startupPre-startup safety reviewBefore it runs, confirm it was built as designed and the procedures, training and safeguards are ready.
- Like for like isn't a changeReplacement in kindA part that meets the same design specification as the one it replaces doesn't need a review.
Why changes cause incidents
A workplace's safeguards were built around how things were: the guard fits the old machine, the procedure describes the old chemical, the training covers the old layout. A change can quietly undo any of them without anyone deciding to.
Small changes add up the same way. A setting nudged here, a step skipped there, a substitute part that's "basically the same." And temporary changes have a way of staying: nothing is as permanent as a temporary fix.
Management of change (MOC) is the habit of stopping to look before a change goes in. Pre-startup safety review (PSSR) is the last look before it runs.
The steps
- Step 1Propose the changeWhat, why, and for how long
- Step 2Review the hazardsWhat the change could do to people
- Step 3Approve itSomeone with the authority signs
- Step 4Update and trainProcedures, drawings, the people affected
- Step 5Pre-startup reviewBuilt as designed, everything ready
- Step 6Start upThen watch it run
What OSHA requires at process safety sites
OSHA's Process Safety Management standard (29 CFR 1910.119) covers processes with highly hazardous chemicals above set amounts, such as 10,000 pounds or more of certain flammable liquids or gases at one location. At those sites, MOC is required in writing.
The procedures have to cover changes to process chemicals, technology, equipment, procedures, and facilities that affect a covered process, except replacements in kind. Before any change, they have to address:
- the technical basis for the change;
- its impact on safety and health;
- changes to operating procedures;
- how long the change will be in place; and
- who has to authorize it.
Operators, maintenance workers and contract employees whose work the change affects are informed and trained before startup, and the process safety information and operating procedures are updated to match.
Pre-startup safety review
The same standard requires a pre-startup safety review for new facilities, and for changed ones when the change is big enough to change the process safety information. Before the hazardous chemical is brought in, the review confirms that:
- construction and equipment match the design specifications;
- safety, operating, maintenance and emergency procedures are in place and adequate;
- a new facility's process hazard analysis is done and its recommendations resolved, or a changed facility has met the management of change requirements; and
- everyone who operates the process has been trained.
Not a process safety site? It's still worth doing
Most workplaces aren't covered by Process Safety Management, but their changes bring hazards all the same. OSHA's Recommended Practices for Safety and Health Programs say that before changing operations, workstations or workflow, making major organizational changes, or bringing in new equipment, materials or processes, a site should ask its workers and evaluate the planned change for hazards.
OSHA's 2026 VPP manual asks the same of VPP sites: a pre-use analysis of new equipment, chemicals, facilities and significantly different ways of working, as detailed as the risk calls for.
The changes worth a look usually fall into a few kinds:
- a machine or piece of equipment, new or modified;
- a material or chemical;
- how the work is done;
- controls and software;
- people and roles, such as staffing or who covers a job; and
- the building or the layout of an area.
Temporary changes are changes too
A temporary change gets the same review as a permanent one, plus an end date. When the date comes, it's put back, or it's reviewed again as a permanent change. A temporary change with no end date is just a permanent change nobody reviewed.
Why it matters
A hazard found on paper costs an email. The same hazard found after startup costs a retrofit, a shutdown, or an injury. MOC is the cheapest point in a change's life to make it safe, and the people who will run it are usually the first to spot what the drawings missed.
PraxysEHS Management of Change reviews a new machine, material or way of working before it's bought, built or moved, with the factory test and pre-startup safety review as steps that can't be skipped.
See Management of Change